206 Project management tools and techniques
project to make sure that there is a safe back-up system to handle poten-
tial operational downtime. At this point, since historical records from the
organization only show the issue of temporary downtime, do we end the
identication of risks stage or keep brainstorming other potential risk
scenarios? The latter option is correct as the realities of life indicate that
there are always new situations to consider. Realize that history may not
be a complete educator for future situations. Therefore, the project team
should be diligent in reviewing both historic and less obvious future situ-
ations in thei ...