chapter seven
Developing the work breakdown
structure
Introduction
The origin of a modern project WBS can be traced to the latter 1950s as a
result of successful implementation of the highly technical Polaris mis-
sile project. The project management-oriented acronym terms PERT and
WBS became popularized as a result of that effort (Haugan 2002). The
WBS model became a commonly used project tool by the 1960s and is
now a visible concept in all project management standards documents.
PERT over the same period has had mixed success as a time manage-
ment-oriented model. This chapter will focus on showing how the WBS
model has achieved broad impa