Resource leveling
Introduction to resource leveling
The fundamental wish list of PMs is that they have unlimited labor and
monetary resources to perform the project work. However, the reality
is that many PMs have this wish list in mind but management does not
understand the operational signicance of this. The unfortunate conse-
quence of this is that there is a mismatch between the plan and actual
resource availability. Therefore, management never actually commits the
needed resources to successfully perform the planned work. There are two
common problems faced by projects and that is setting a realistic date for
deliverab ...