154 Project management tools and techniques
To help rene the plan as it evolves all of the estimates and associated
assumptions related to this activity should be captured in the WBS dic-
tionary for use in subsequent steps.
Estimating activity durations
Duration estimates are driven by decisions related to work effort by vari-
ous labor skills. To translate work into activity duration, it is necessary to
dene the number of actual bodies by skill type to be allocated into that
work unit. This in turn yields the planned work duration of the activity. To
illustrate this point, assume that the work package activity is dened to be
160 hours of work. Assuming the skill required is dened, the next step in
the sequence involves the actual work s