34 Project management tools and techniques
Table 2.8 Project XYZ Mini Review
Date of review 2/22/12
% Complete of plan 67%
Reviewers Julie Smith
Seq Metric
Rating
0 = Good
5 = Poor Comments
1 Critical path (longest
sequence of tasks and
controls the nish date)
5 There are a number of “level of
effort (LOE)” tasks (i.e., handle
issues, attend meetings, monitor
project, etc.) that are on the
critical path and there is an
average of 1-week delay
2 Deliverables by phase 0 The solution outline is scheduled
to complete within 2 days of
original completion date
3 Late milestones (zero
duration that achieves
a deliverable or key
point in the project)
5 There ar ...