227
chapter thirteen
Finalizing the project plan
The previous chapters have described the mechanics for creating, sizing,
communicating, and receiving approval of the project plan. Recall that
components of the project plan consist of schedule, budget, risk, and vari-
ous nondirect items. At this point, the management and key stakeholders
have signed off on the document and the project team is now gearing up
to move into execution. From this base point, it is necessary to execute
the nal set of steps to formally terminate the planning stage and tran-
sition into the execution phase. Before jumping into this discussion, be
aware that the materia ...