164 Project management tools and techniques
Several other slack-type status parameters can be derived from this
view. The most interesting ones are Total Float, Free Float, and Late Finish.
Each of these relates to activity views rather than node calculations, but
this same value set can be derived from the node values. Total Float relates
to the amount of activity slack (variability) before project completion is
impacted, while Free Float deals with the same view only for the succes-
sor activity. Late Finish describes the latest time that the activity can be
completed without impacting the schedule. Since these arrows represent
required projec ...