179Chapter ten: Creating the project budget
The total available supply source of labor, material, and cost items are
dened in the resource pool. From this, the planning process will allocate
some quantity of a resource to specic work units. This allocation will
then produce duration and direct cost for that item. When linked to the
work unit predecessor data, a project schedule is generated as was dem-
onstrated in the previous chapter, except that we now have direct cost
included in the plan. A total direct cost for the that work units is calcu-
lated and a time-phased distribution of that cost is phased through time
by the predecessor logic.
Direct material costs are more complex to accurately calculate since
this class of resource is of ...