122 Project management tools and techniques
there is an old adage that says you cannot get nine women to have a baby
in one month. So, it is with most tasks.
We leave this hole-digging example to be pondered. Which of these
options should be selected and for what reasons? In most situations, this
boils down to deciding which of the goals is highest (time, cost, quality,
control, happiness, etc.). Hopefully, this discussion illustrates that the pro-
cess of estimating has many “interesting” subplots.
Denitional process
Several estimating vocabulary variables are embedded in the hole-digging
example. We rst started off with dening the level of work. From this
came a calculation of duration based on allocated resources. Finally, based
on various ...