Understanding both critical path and slack concepts is vital for effec-
tive time management and requires that the PM keep these parameter val-
ues in mind as the project unfolds. Also, recognize that errors in duration
estimates will cause the slack values to change during project execution,
so this is not a static view by any stretch. Understanding activity slack or
oat gives the PM exibility in scheduling the start of a particular activity
(Uher 2003). This also helps to facilitate prioritization of resource alloca-
tions across the project plan. For example, if there are two activities occur-
ring within the same time range, one critical and one noncritical that are
competing for the same re ...