397Chapter twenty-two: Risk mechanics
response. Following a plan that was written in advance helps the team be
proactive with the goal of enhancing opportunities and reducing threats
to the project’s objectives.
The four different risk strategies are accept risk, avoid risk, mitigate
risk, and transfer risk. As discussed previously in Chapter 11, identifying
the root cause of a risk or risks helps to understand the reason why the risk
could occur, which brings insights into whether a risk will be accepted,
avoided, mitigated, or transferred. Sheehan (2010) suggests that a risk be
accepted if the likelihood of the risk occurring and the nancia ...