174 Project management tools and techniques
this, but many other causal factors exist as well. Two other mechanical
allocation-oriented factors are poor initial requirements denition and
poor scope control. Three broader categorizations of explanation for cost
overrun are
• Technical factors create cost overruns from imperfect forecasting
techniques, inadequate data, and so on.
• Psychological factors account for overruns in terms of optimism bias
with forecasters. A belief in the lack of future scope creep is one
example of this.
• Political−economic explanations can cause overruns as the result
of instability in either of these macro en