302 Project management tools and techniques
It is typical for the project performance statistics to drift away from
baseline values during execution. For example, Figure 16.3 indicates a ve
work day variance in the nish date from 7/18/11 to 7/25/11. The same
duration variance is indicated between current duration and baseline
duration (or 148d–143d).
The bottom-half of the dialog box indicates changes to most of the
nonbaseline elds. The current eld data items are related to the current
plan values and these are compared to the approved baseline values. It is
important to note that the work hours increased by 98.5 (or 200.75–102.25)
and t ...