STRATEGIC LE A D -T I ME M A N A GEMENT
129
Overcoming these problems and ensuring timely response to volatile demand
requires a new and fundamentally different approach to the management of
lead times.
Logistics pipeline management
The key to the successful control of logistics lead times is pipeline management.
Pipeline management is the process whereby manufacturing and procurement
lead times are linked to the needs of the marketplace. At the same time, pipeline
management seeks to meet the competitive challenge of increasing the speed of
response to those market needs.
The goals of logistics pipeline management are:
Lower costs
Higher quality
More flexibility
Faster response times
The achievement of these goals is dependent upon managing the supply chain
as an entity and seeking to reduce the pipeline length and/or to speed up the flow
through that pipeline. In examining the efficiency of supply chains it is often found
that many of the activities that take place add more cost than value. For example,
moving a pallet into a warehouse, repositioning it, storing it and then moving it out
in all likelihood has added no value but has added considerably to the total cost.
Very simply, value-adding time is time spent doing something that creates a
benefit for which the customer is prepared to pay. Thus we could classify man-
ufacturing as a value-added activity as well as the physical movement of the
product and the means of creating the exchange. The old adage ‘the right product
in the right place at the right time’ summarises the idea of customer value-adding
activities. Thus any activity that contributes to the achievement of that goal could
be classified as value adding.
On the other hand, non-value-adding time is time spent on an activity whose
elimination would lead to no reduction of benefit to the customer. Some non-value-
adding activities are necessary because of the current design of our processes but
they still represent a cost and should be minimised.
The difference between value-adding time and non-value-adding time is crucial
to an understanding of how logistics processes can be improved. Flowcharting
supply chain processes is the first step towards understanding the opportunities
that exist for improvements in productivity through re-engineering those processes.
Once processes have been flowcharted, the first step is to bring together
the managers involved in those processes to debate and agree exactly which
The longer the pipeline from source of materials to the final user the less
responsive to changes in demand the system will be.
LOGISTIC S & SUPPLY CHAIN MANAGEMENT
130
elements of the process can truly be described as value adding. Agreement may
not easily be achieved as no one likes to admit that the activity they are responsi-
ble for does not actually add any value for customers.
The next step is to do a rough-cut graph highlighting visually how much time is
consumed in both non-value-adding and value-adding activities. Figure 6.8 shows
a generic example of such a graph.
Figure 6.9 shows an actual analysis for a pharmaceutical product where the total
process time was 40 weeks and yet value was only being added for 6.2 per cent of
that time.
It will be noted from this example that most of the value is added early in
the process and hence the product is more expensive to hold as inventory.
Furthermore, much of the flexibility is probably lost as the product is configured
and/or packaged in specific forms early in that process. Figure 6.10 shows that
this product started as a combination of three active ingredients but very rapidly
became 25 stock keeping units because it was packaged in different sizes, for-
mats, etc., and was then held in inventory for the rest of the time in the company’s
pipeline.
The difference between value-adding time and non-value-adding time is
crucial to an understanding of how logistics processes can be improved.
Raw
material
stock
Production
Finished
product
In-transit
Regional
stock
Customer
order
cycle
Cost added
Production, storage and transport costs and the time cost of money
Value
added
Time,
place and
form
utility
Figure 6.8 Which activities add cost and which add value?
STRATEGIC LE A D -T I ME M A N A GEMENT
131
10%
20%
30%
40%
50%
60%
70%
80%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39
Weeks in the supply chain
• 6.2 per cent of value-added time over a 40-week supply chain
Supplier lead time
Inbound material
Primary conversion
Secondary
conversion
Packaging
Shipment
Distributor
Ship to customer
Distribution centre pick
% of total cost added by logistics processes
Figure 6.9 Value added through time
Get Logistics and Supply Chain Management, 4th Edition now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.