GAME PLAN 271
approved, level production comes to a standstill, valuable time is lost, and a
bottleneck is created. Additionally, if someone is overloaded with too many tasks,
they cannot keep up the same pace of work as others involved in the level pro-
duction process and will cause delays. So it is important to make sure that the
correct dependencies and resource allocations are included in the schedule. The
importance of this is best shown in Figures 16.4, 16.5, 16.6, and 16.7.
Figure 16.4 is a detailed level production schedule for the Villain’s Lair.
This does not include any task dependencies or assigned resources. Based on
FIGURE 16.4 ...