Key Equations

Developing the Project Schedule

  1. 1. Start and finish times:

    t=estimated time duration of the activityES=latest of the EF times of all activities immediately preceding activityEF=ES+tLF=earliest of the LS times of all activities immediately following activityLS=LFt

  2. 2. Activity slack:

    S=LSES or S=LFEF

Analyzing Cost–Time Trade-offs

  1. 3. Project costs:

    Crash cost per period=Crash costNormal costNormal timeCrash time=CCNCNTCT

Assessing and Analyzing Risks

  1. 4. Activity time statistics:

    te=mean of an activity's beta distributionte=a+4m+b6σ2=variance of the activity timeσ2=(ba6)2

  2. 5. z-transformation formula:

    z= T T E σ P

    where

    T=due date for the projectTE= (expected activity times on the critical path)=mean of normal distribution of critical path time ...