Solved Problem 2
The Food Bin grocery store operates 24 hours per day, 7 days per week. Fred Bulger, the store manager, has been analyzing the efficiency and productivity of store operations recently. Bulger decided to observe the need for checkout clerks on the first shift for a 1-month period. At the end of the month, he calculated the average number of checkout registers that should be open during the first shift each day. His results showed peak needs on Saturdays and Sundays.
Day
M
T
W
Th
F
S
Su
Number of Clerks Required
3
4
5
5
4
7
8
Bulger now has to come up with a workforce schedule that guarantees each checkout clerk 2 consecutive days off, but still covers all requirements.
Develop a workforce schedule that covers all requirements ...