The following data were reported by the shop floor control system for order processing at the edge grinder. The current date is day 150. The number of remaining operations and the total work remaining include the operation at the edge grinder. All orders are available for processing, and none have been started yet. Assume the jobs were available for processing at the same time.
Current Order |
Processing Time (hr) |
Due Date (day) |
Remaining Operations |
Shop Time Remaining (days) |
|---|---|---|---|---|
A101 |
10 |
162 |
10 |
9 |
B272 |
7 |
158 |
9 |
6 |
C105 |
15 |
152 |
1 |
1 |
D707 |
4 |
170 |
8 |
18 |
E555 |
8 |
154 |
5 |
8 |
Specify the priorities for each job if the shop floor control system uses slack per remaining operations (S/RO) or critical ratio (CR).