Solved Problem 1
Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table 7.2.
MyLab Operations Management Video
Table 7.2 Electric Motor Project Data
Activity
Normal Time (days)
Normal Cost ($)
Crash Time (days)
Crash Cost ($)
Immediate Predecessor(s)
A
4
1,000
3
1,300
None
B
7
1,400
4
2,000
None
C
5
2,000
4
2,700
None
D
6
1,200
5
1,400
A
E
3
900
2
1,100
B
F
11
2,500
6
3,750
C
G
4
800
3
1,450
D, E
H
3
300 ...
Get Operations Management: Processes and Supply Chains, 12th Edition now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.