Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table 7.2.
Activity |
Normal Time (days) |
Normal Cost ($) |
Crash Time (days) |
Crash Cost ($) |
Immediate Predecessor(s) |
|---|---|---|---|---|---|
A |
4 |
1,000 |
3 |
1,300 |
None |
B |
7 |
1,400 |
4 |
2,000 |
None |
C |
5 |
2,000 |
4 |
2,700 |
None |
D |
6 |
1,200 |
5 |
1,400 |
A |
E |
3 |
900 |
2 |
1,100 |
B |
F |
11 |
2,500 |
6 |
3,750 |
C |
G |
4 |
800 |
3 |
1,450 |
D, E |
H |
3 |
300 ... |