We use the learning curve formulas to calculate the time required for the 38th unit:
Table I.1 gives the data needed to calculate the cumulative number of hours through each month of the schedule. Table I.2 shows these calculations.
Month |
Cumulative Units |
Cumulative Average Time per Unit |
Cumulative Total Hours/Month for All Units |
|---|---|---|---|
1 |
3 |
||
2 |
10 |
||
3 |
20 |