For a time study of a health insurance claims-adjusting process, the analyst uses the continuous method of recording times. The job is divided into four work elements. Shown in Figure H.3 are the performance rating factors, RF, and the continuous method recorded times, r, for each work element.

Calculate the normal time for this job.
Calculate the standard time for this job, assuming that the allowance is 20 percent of the normal time.
What is the appropriate sample size for estimating the time for element 2 within percent of the ...