342 A First Course in Quality Engineering
An example (from Boyles 1992) that assumes the usual two-sided specica-
tion with the target at the center of the specications is shown in Figure 5�20�
In this gure, all three processes (A, B, and C) have the same specications
and target but have different process means and standard deviations�
Looking at Process A, when the process mean is at the center of the spec-
ication, which is also the target, the values of C
p
, C
pk
, and C
pm
are all the
same� In Processes B and C, when the process standard deviation decreases,
the C
p
values increase, but the values of C
pk
and C
pm
are smaller compared to
C
p