142 Scaling BPM Adoption from Project to Program with IBM Business Process Manager
It is important to have new employees integrated into the business and being
productive as soon as possible. The call center training is planned to start on
day 4 of a new employee’s arrival. The training is a significant cost, and the
employee needs equipment to reap optimal benefits from the training. Therefore,
the necessary equipment must be issued by the end of day 3.
This brings us to our second SLA,
employee setup time:
The
facilitate new hire’s orientation subprocess must be finished within three
days from the start date of a new employee.
In concrete terms, this means that the
total time KPI for facilitate new hire’s
orientation
activity cannot exceed ...