One of the biggest problems with activity-specific sprints is that they create what are known as finish-to-start relationships. In a finish-to-start relationship, one task must finish before the next can start. For example, a Gantt chart on a sequential project may show that analysis must finish before coding can start and that coding must finish before testing can start. Good Scrum teams learn that this is not true; many activities can be overlapped. What is important is not when tasks start but when they finish. Coding cannot finish until analysis finishes and testing cannot finish until coding finishes. These are known as finish-to-finish relationships and are reinforced by ...