Because few organizations will go so far initially as to completely revamp their current approaches to governance, teams will need ways to work with their organization’s non-agile governance. Taking the following actions should help.
Undoubtedly, the first Scrum project to go through the governance process in your company will have challenges. There will almost certainly be some things they cannot do; for example, a Scrum team cannot provide a thorough design before getting permission to start coding, because design and coding will be done concurrently. The only solution to this is for the team to negotiate with the necessary governance groups in advance. ...