Going from Estimate to Commitment
The three arrows in Figure 15.4 still show only estimates. For many projects, it will be necessary to translate those estimates into commitments. I would ideally like to convert these estimates into a commitment by saying something like, “In the next 5 sprints we believe we can commit to delivering between 170 [5 × 34] and 205 [5 × 41] story points, which means we’ll deliver between here [top arrow] and there [bottom arrow] on the product backlog.” This is the most realistic and accurate commitment. However, in many cases, product owners and their teams are asked to give a point estimate—“We commit to finishing exactly here.” This is often the case for an organization doing outsourced, contract development work ...