Adding resources

Another common way organizations may try to get a project back on schedule is to add more resources. However, this approach doesn't necessarily allow a project to be completed faster, and it may cause the project to take even longer. Brooks' Law, from The Mythical Man-Month, states that ...adding human resources to a late software project makes it later.

As you add more people to a project, the communication paths increase in a multiplicative way. In addition to taking more time to communicate, many more opportunities for miscommunication are created. Productivity and the number of defects (both in requirements as well as design and implementation) are known to increase as projects get larger.

If the team is going to add ...

Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.
Start your free trial

You might also like

Solutions Architect's Handbook

Solutions Architect's Handbook

Saurabh Shrivastava, Neelanjali Srivastav
Solutions Architect's Handbook - Second Edition

Solutions Architect's Handbook - Second Edition

Saurabh Shrivastava, Neelanjali Srivastav
Software Architecture in Practice, 4th Edition

Software Architecture in Practice, 4th Edition

Len Bass, Paul Clements, Rick Kazman
Solutions Architect's Handbook - Third Edition

Solutions Architect's Handbook - Third Edition

Saurabh Shrivastava, Neelanjali Srivastav

Publisher Resources

ISBN: 9781788624060Other