Refine the initial duration estimates using factors specific to your project such as:
Project constraints and assumptions
Any unclear project specifications from scope planning
Any known delays or requirements for synchronization of work from activity sequencing
Probable scope changes
Technical complexity
Requirements for unusually high reliability or performance
Overall project length
Requirements for innovation, investigation, or invention
Training
Duration and effort estimates (from cost estimation) are closely linked. Which you do first for project planning does not matter much, but reconcile them before finalizing a baseline plan. Adjust any estimates of duration to ensure consistency ...