Check that each activity and milestone is linked backward to at least one predecessor (except for the initial milestone) and forward to at least one successor (except for the final milestone). Ensure continuity of workflow on each path in the network. If you find logical gaps where you are missing work necessary to connect defined activities, describe it and add it to the work breakdown structure of your scope definition.
Use the graphical representation of the project to support schedule development and critical path analysis. Some other names for this network diagram are:
Logical project ...