Analyze the staffing for project activities using a two-dimensional matrix listing the defined project activities on one axis and the project staff by name on the other. Include an extra slot on the staffing axis to keep track of staffing needs that are not yet met. A simple example:
| Hawkeye | Margaret | Trapper | Radar | tbh | |
|---|---|---|---|---|---|
| Activity 1.1.1 | O | C | A | C | |
| Activity 1.1.2 | R | O | |||
| Activity 1.2.1 | C | C | O | R | CCC |
| Activity 1.2.2 | A | O | C | C |