Schedule control is central to project plan execution. It follows status collection and plan variance analysis in the project tracking cycle. It is necessary in any cycle where you discover a significant schedule variance. For each variance, review its root cause and impact on the project timeline. Determine whether the impact is a one-time or short-term issue, or whether the root cause is a longer term chronic problem.